Land at Burgate Acres Salisbury Road Burgate

Reference: 20/10228

Status: Decided and works started on site.

Proposal: 

  • erection of 63 dwellings
  • creation of new access
  • parking
  • landscaping
  • open space and associated works (following demolition of existing buildings)

 

Updates

August 2024

  • The Site Monitoring Officer and Ecologists have carried out a site inspection of the required ecological features. The two bat boxes required to be installed have been placed in the ANRG. The two reptile hibernacula required to be installed have also been placed in the ANRG. The hedgehog highways have been created in the fences. Most of the ecological features have now been installed on site. There is only one House Martin nest box left to install.
  • The grass seed has been completed in the ANRG (Alternative Natural Recreational Greenspace).
  • The ANRG and the two completed play areas are all open to the public.
  • There have been no problems with mud on the roads reported.
  • There have been no problems with noise reported.
  • The roads and hardscaping continue to be installed. The whole site now has solid roadways. This makes it a cleaner site.
    • Plots 42, and 50-53, 56, 57 and 59 are at the internal and external stages.
    • Plots 1-11, 13-39, 41, 43-48, 54, 55, 58 and 60-63 are occupied. Plots 40 and 49 have been sold, but are not occupied yet.
    • Plot 12 is the Sales house.

 

July 2024

  • The two bat boxes required to be installed have been placed in the ANRG.
  • There have been no problems with mud on the roads reported.
  • There have been no problems with noise reported.
  • The hardscaping is being installed around the houses at the Northern end of the site.
    • Plots 41, 42, and 50-57 and 59 are at the internal and external stages.
    • Plots 1-11, 13-39, 43-48, 58 and 60-63 are occupied. Plots 40 and 49 have been sold, but are not occupied yet.
    • Plot 12 is the Sales house.

 

June 2024

  • There have been no problems with mud on the roads reported.
  • There have been no problems with noise reported.
  • The kerbs are being installed adjacent to Plots 53-57.
  • The tarmacking of the main spine road is taking place in the Northern section of the site.
  • The area of ANRG (Alternative Natural Recreational Greenspace) adjoining the houses on its Eastern edge, has been grass seeded along with other pockets of open space along that stretch of the site. The grass is beginning to grow now. 
  • The landscapers are continuing with the planting across the site.
  • More of the Ecological features have been installed, both on the houses and in the ANRG. The site manager has been given a list of the remaining ones so they can be installed in the short term. 
    • Plots 41, 42, and 49-59 are at the internal and external stages.
    • Plots 1-11, 13-38, 43-48 and 60-63 are occupied. Plots 39 and 40 have been sold, but are not occupied yet.
    • Plot 12 is the Sales house.

 

April 2024

  • There have been no problems with mud on the roads reported.
  • There have been no problems with noise reported.
  • The area of ANRG (Alternative Natural Recreational Greenspace) adjoining the houses on its Eastern edge, will be grass seeded once the wet weather eases off.
  • Fencing works in the ANRG continue to be carried out, along with general housekeeping works.
  • The landscapers are continuing with the planting across the site. NFDC officers will be carrying out a site inspection of all the planting next month.

 

March 2024

  • The dog agility equipment has been installed.
  • The area of the ANRG (Alternative Natural Recreational Greenspace) adjoining the houses on its Eastern edge, is being landscaped. The pathways and fencing are being constructed. Tree planting is also taking place in that area.
  • The central play area in the ANRG has been turfed and planted up. Offcuts from the tree works have been used to create bug and small creature habitats.
  • The landscapers are continuing with the planting on site. They have been planting the area around Plots 16-19 and the open space there.
  • The Site Monitoring Officer and the NFDC Ecologist recently made a site inspection of the Ecological features attached to the houses and in the ANRG, to ensure compliance.

 

January 2024

  • There is no problem with mud on the roads at the moment. The site is still using the road sweeper to keep the roads clean.
  • The block paving has been installed adjoining Plots 36-38. The rear walls to the plots are being constructed. The garage doors have also been installed.
  • The contractor has ordered in the remaining Ecological features, ready to get them installed as the build permits.
  • The Open Spaces Officer met the contractor on site to make sure the play equipment and dog agility equipment is compliant.
  • The landscapers are continuing with the planting on site.
  • Plots 41, 42 and 49-53 are at first floor level.
  • Plots 45, 46, 58 and 60 are at roofline.
  • Plots 3, 5, 16-19, 36-40, 43, 44, 47, 48, 54-57, 59 and 61-63 are at the internal and external stages.
  • Plots 1, 2, 4, 6-11, 13-15 and 20-35 are occupied.
  • Plot 12 is the Sales house.
  • The Sales Executive on site has advised the following:
    • Plot 12 is the Sales house.
    • Plots 1, 2, 4, 6-11, 13-15 and 20-35 are occupied.
    • Plots 19, 37, 38, 39, 40, 49, 50, 51, 52, 54, 56, 57, 58 are for sale.
    • Plots 36, 42, 47, 59, 60, 61, 62 and 63 are reserved.
    • Plots 16, 17, 18, 41, 43, 44, 45, 46, 48 and 55 have exchanged.
    • The next occupations are due by the end of February.

 

December 2023

  • The building work is progressing well, with Plots 20-27 having been handed over. The deputy site manager informed me that Plots 20, 23, 24, 26 and 27 are now occupied. 
  • A site meeting involving officers from NFDC and the developer was held recently to inspect the ANRG (Alternative Natural Recreational Greenspace). Actions were agreed to make sure the land would be ready for transfer. 
  • The outstanding ecological features have been chased with the deputy site manager. They're being installed in the short term so that the houses concur with the ecological details prior to occupation. All the houses that are already occupied, or will be soon, have the correct ecological features already installed.
  • The kerbstones are being installed in the Northern section of the site, commencing by Plot 63.
  • The Hampshire Highways team have confirmed that the permissions have been issued for both the Northern pathway joining FORD1 to Burgate Acres and for the path at the top end. They can now progress these works.
  • Plots 51-53 are at ground floor level.
  • Plots 41, 42, 49 and 50 are at first floor level.
  • Plots 43-48, 54-58 and 60-62 are at roofline.
  • Plots 1-11, 16-19, 21, 22, 25, 29, 30, 32-40, 59 and 63 are at the internal and external stages.
  • Plots 13-15, 20, 23, 24, 26, 27, 28, and 31 are occupied.
  • Plot 12 is the Sales house.
  • Plots 19, 37, 58 and 60 are for sale.
  • Plot 38 has been reserved.
  • Plots 16-18, 21, 22, 25, 32, 36, 41, 42, 43, 44, 45, 46, 47, 48, 55, 62 and 63 have exchanged.
  • Plots 13-15, 20, 23, 24, 26, 27, 28, and 31 are occupied.
  • Plot 12 is the Sales house.

November 2023

  • The build is progressing well. The South-Western corner, especially, is really taking shape. Plots 16-19 (flats) are at the internal and external stages. The kerbs are going in for the spur road and the car ports have been built.
  • The landscaping contractor has commenced the planting in the North-Eastern section of the site. The play area equipment has been installed in the ANRG (Alternative Natural Recreational Greenspace) and the contractor is laying the play surface.
  • The post and rail fence has also been installed. The paths have been constructed in this area. They will be inspected to ensure that they concur with the agreed details. 
  • The dog agility equipment has been ordered and is expected at the site in the short term when it will be installed.
  • The integral bat tubes are being installed on the houses in the Northern section of the site alongside the cladding that is due to be fitted soon.
  • Plots 41, 42 and 49-53 are at ground floor level.
  • Plots 43-48, 54-58 and 60-62 are at roofline.
  • Plots 1-11, 16-40, 59 and 63 are at the internal and external stages.

October 2023

  • The clearance work in the ANRG (Alternative Natural Recreational Greenspace) has been taking place. The contractor is currently constructing the no-dig (raised) footpaths. The planting should take place between October and March.  
  • Plots 41, 42 and 50 have their foundations and service access points in.
  • Plots 49 and 51-53 have their slabs constructed.
  • Plots 43-46 and 56-58 are at first floor level.
  • Plots 16-19, 47, 48, 54, 55 and 59-63 are at roofline.
  • Plots 1-11, 20-40 are at the internal and external stages. 
  • Plots 13-15 are occupied.
  • Plot 12 is the Sales house.
  • Plots 29, 30 and 32-35 are having the car ports constructed 

August 2023

  • The roads remain clear of mud along the stretch that is now occupied out to the main road.
  • Plots 41, 42 and 50 have their foundations and service access points in.
  • Plots 49 and 51-53 have their slabs constructed.
  • Plots and 43-48, 54-57, 59 and 60 are at ground floor level.
  • Plots 58, 61 and 62 are at first floor level.
  • Plots 1-5, 16-19, and 36,39, 40 and 63 are at roofline.
  • Plots 6-11, 20-35, 37 and 38 are at the internal and external stages. With Plots 32, 37 and 38 ready to be made watertight.
  • Plots 13-15 are occupied.
  • Plot 12 is the Sales house.
     

June 2023

  • The wildflower seeding at the entrance to the site (on the bund to the left hand side) is due to be carried out at the end of May . 
  • Plot 12 is going to be the show home.
  • Plots 13-15 are oc
  • The roads are clearer of mud along the stretch that is now occupied out to the main road.
  • There are no problems with noise.
  • Plots 48-53 have their foundations and service access points in.
  • Plots 59 and 60 have their slabs constructed.
  • Plots and 43-47, 54-58 and 61-63 are at ground floor level.
  • Plots 36-42 are at first floor level.
  • Plots 1-5, 16-19, 23-26, 31 and 32 are at roofline.
  • Plots 6-11, 20-22, 27-30 and 33-35 are at the internal and external stages.
  • Plot 12 is the Sales house.

 

May 2023

  • The wildflower seeding at the entrance to the site (on the bund to the left hand side) is due to be carried out at the end of May . 
  • Plot 12 is going to be the show home.
  • Plots 13-15 are occupied.
  • Plots 6-11, 29, 30 and 33-35 are at the internal and external stages.
  • Plots and 36-40, 58 and 61-63 are at ground floor level.
  • Plots 16-19 are at first floor level.
  • Plots 1-5, 20-28, 31 and 32 are at roofline.
  • Plots 43-48, 56, 57, 59 and 60 have their slabs constructed.
  • Plots 41, 42, and 49-55 have their foundations and service access points in.

 

April 2023

  • Some tree planting has taken place along the Eastern boundary adjoining Plots 36-45. This will provide some privacy and a green boundary edge as it matures. No other planting has been carried out in the open space on site.
  • The trees due to be planted in the ANRG are programmed in to be completed by the end of April.
  • The playground equipment has been ordered and would be installed in May.
  • The bund forming the edge of POS 1 has been formed. This will now need to be seeded.
  • Plots 1-5 have just commenced first floor level. Plots 6-15 are at the internal and external stages.
  • Plots 16-19, 32, 34, 35 and 36-38 are at ground floor level.
  • Plots 20-27, 28 and 31 are at first floor level.
  • Plots 29, 30 and 33 are at roofline.
  • Plots 39, 40, 56-59, 62 and 63 have their slabs constructed.
  • Plots 41-55 have their foundations in.
  • Plots 12, 16, 18, 31 and 41 have been reserved.
  • Plots 20-27 have exchanged.
  • Plots 13, 14 and 15 are due to complete and be occupied today.

 

March 2023

  • Plots 1-5 have commenced construction. They are at ground floor level. Plots 6-15 are at roofline. They have commenced their interior works.
  • Plots 29, 30, 33-35 are at first floor level. The car parking for this area is currently being constructed. Plots 20- 28, 31 and 32 are at ground floor level. Plots 16-19 have their slabs in.
  • Plots 36-38 are at ground floor level. 39-40 have their slabs in. 47-61 have their foundations, drainage and water service points in. The parking spaces for Plots 52 and 53 have been constructed. The access road to
  • Plots 58-63 is being constructed. Plots 62 and 63 have their slabs in.
  • The tree protection remains in place across the site to protect the open space areas and tree root protection zones.
  • The developer is continuing work on the ANRG (Alternative Natural Recreational Greenspace).

 

January 2023

  • The highway entrance to site has been completed.
  • Plots 1-5 have commenced construction. Their footings are in. Plots 6-15 are at roofline.
  • Plots 29, 30, 33-35 are at ground floor level. The car parking for this area is currently being constructed. 
  • Plots 28, 31, 32 have their slabs in. Plots 23-27 are at ground floor level. Plots 16-20 have commenced construction. 
  • Plots 16-19 have their footings in. Plots 20-22 are at ground floor level.
  • Plots 36-42 have their foundations, drainage and water service points in. The roadway into this section of the site has commenced construction.
  • Plots 43-46 have commenced construction. Their foundations are in.
  • Plots 47-50 and 56-63 have their foundations, drainage and water service access points in. The access road to Plots 58-63 is being constructed.
  • Plots 51-55 have commenced construction. They too have their foundations, drainage and water service access points in.
  • The tree protection remains in place across the site to protect the open space areas and tree root protection zones.
  • The developer is continuing work on the ARNG (Alternative Natural Recreational Greenspace).

December 2022

  • The roadways adjoining the entrance and the crossing are being constructed. The grass seeding of the nonpaved areas has been carried out.
  • The roads are continuing construction throughout the site, both the spine and spur roads.
  • The tree protection is in place across the site to protect the open space areas and tree root protection zones.
  • The developer has started work on the ARNG (Alternative Natural Recreational Greenspace). They are carrying out the clearance of brambles. The pathways are due to be constructed along with the play areas prior to 1st occupation.  This is expected to be in March.  Both the ARNG and the play areas need to be completed and open prior to this. 
  • Plots 6-15 are having their 1st floor walls constructed.
  • Plots 16-19, 23-28, 31 and 32 are having their slabs constructed.
  • Plots 29, 30 and 33-35 are having their ground floor walls constructed.
  • The construction of the spur roads is being carried out at the Northern end of the site. The road drainage is going in.
  • Plots 56-63 have their foundations and service access points in, both for the water and the drainage.
  • Plots 47-50 have commenced construction. Their foundations are being constructed.
  • Plots 36-42 have their foundations and service access points are in, both the water and the drainage.

 

November 2022

  • The main road into the site is being constructed. The kerbs and services are going in  with the tarmac top layer being laid at the end of October.
  • The spine road through the site to the Northern end is being constructed. The kerbs are going in currently. 
  • The POS (Public Open Space) and ANRG (Alternative Natural Recreational Greenspace) areas have been fenced off to protect them.
  • Plots 36, 37, 38, 39, 40 have their foundations in and the water and drainage lines have been installed.
  • Plots 62, 63 have their foundations in.
  • Plots 56-61 are having their foundations constructed. The existing house is being demolished currently.
  • Plots 23-28, 31 and 32 have their foundations constructed and their drainage and water service lines installed.
  • Plots 6-15, 29, 30 and 33-35 have their slabs constructed and are currently having their ground floor walls constructed.

 

September 2022

  • The Northern end of the site has been cleared and is now being used as a materials compound as per the agreed plan.
  • The main spine road into the site has been constructed, for site traffic to use. 
  • The site compound and welfare units are in situ, as is the site parking.
  • The soakaway serving Plots 1-11 has been constructed. The car park serving these plots is also in situ and is being used for storage of the site vehicles.
  • Plots 6-15, 28-31, and 33-35 have commenced construction. Their foundations are in and the bases are being prepped ready to start construction of the slabs.

 

August 2022

  • Site clearance has taken place across most of the site. The existing dwellings and outbuildings due to be demolished are currently still in situ.
  • The tree protection is in situ. This was checked across the whole of the site against the agreed plan.
  • The Northern end of the site has commenced site clearance with the turf starting to be removed. 
  • The soakaway serving Plots 1-11 is being constructed.
  • Plots 6-14 have commenced construction. The foundations are in and the bases are being prepped ready for the beams to be installed to start creating the slabs.

 

April 2022

Application 20/10228 was presented to our planning committee with a recommendation to allow a further three month period until the end of June 2022 for the completion of the S106 Agreement and the issuing of the Planning Permission.

The decision given was that the Executive Head of Planning, Regeneration and Economy be given authority until the end of June 2022 to complete the S106 Agreement and for the Planning Permission to be issued.  You can read the planning committee report below:

January 2022

Application 20/10228 was presented to our planning committee with a recommendation to allow a further one month period until the end of January 2022 for the completion of the S106 Agreement and the issuing of the Planning Permission.

The decision given was that the Executive Head of Planning, Regeneration and Economy be given authority until the end of February 2022 to complete the S106 Agreement and for the Planning Permission to be issued.  You can read the planning committee report below:

 