2025 updates
Regular monitoring of this site by the Site Monitoring Officer continues.
March 2025
- The installation of the highway road is nearly complete, the adjoining service works continue
- The three-way traffic control set up in the main road adjoining the site has been removed
- The tree protection remains in situ
- The developer is using the wheel washing facilities set up by the entrance to the site and no issues have been reported to date
- The haul road is constructed around the edges of the site
- Landscaping of open space areas has commenced
- Plots 123-125, 128-131, 151-157, 159, 171 and 179-186 are having their foundations constructed
- Plots 172-176, 178 and 206 are at ground floor level
- Plots 191 and 192 are at first floor level
- Plots 198-200 and 205 are at roofline
- Plots 1 - 6, 187-190, 193-197 and 201-204 are at the internal and external stages
- There is no Plot 158 or 177, as per the agreed details
- First occupation is expected in the next couple of months
- The Site Monitoring Office checked the elevations of Plots 187, 188 and 193-196 against the agreed details
February 2025
- Works are continuing on the installation of the highway entrance
- There is a three-way traffic control set up in the main road adjoining the site, contractors are currently carrying out service works
- There are regular deliveries to the site as the build is continuing,the Site Monitoring Officer noted that it was well organised with banksmen and a supervisor directing all traffic to keep the site safe
- The tree protection remains in situ
- The developer is using the wheel washing facilities set up by the entrance to the site and no issues have been reported to date
- Plots 172-176, 178 and 206 are having their foundations constructed, Plot 177 has been deleted due to layout and house type changes and these details have been granted
- Plots 191 and 192 are at slab level
- Plots 198, 199, 200 and 205 are at ground floor level
- Plots 189, 190, 197 and 201-204 are at first floor level
- Plots 187 and 188 are at roofline
- Plots 1 - 6 and 193-196 are at the internal and external stages, the Site Monitoring Officer checked the elevations of Plots 1-6 against the agreed details
- Land is being excavated ready for Plots 171 and 179 -186 to have their foundations constructed