2025 updates
March 2025
- Development is continuing on site
- Plots 1 and 2 are at slab level
- Plots 3 and 4 are at ground floor level
- Plots 5-7 are at first floor level
- Plots 8 and 9 are at roofline
- The agreed tree protection fencing is in situ
February 2025
- Development is continuing on site
- Plots 1 and 2 have their foundations constructed
- Plots 3-5 are at ground floor level
- Plots 6-9 are at first floor level
- The agreed tree protection fencing is in situ