2024 updates
December 2024
- The installation of the drainage works are continuing at the entrance to site, and around the development.
- The construction of the spine road through the site and the spur roads is progressing. The kerbstones are being installed.
- The tree protection remains in situ.
- The developer is using the wheel washing facilities set up by the entrance to the site.
- Plots 101 and 102 are having their foundations constructed.
- Plots 189, 190 198, 199, 200 and 206 are at ground floor level.
- Plots 187, 188 and 195-197 are at first floor level.
- Plots 3, 4, 5, 193 and 194 are at roofline.
- Plots 1, 2 and 6 are at the internal and external stages.
- Land is being cleared and surveyed ready for Plots 171-175 to have their foundations constructed.
November 2024
- The construction of the highway entrance from Station Road in to the site continues. The drainage is still being installed.
- Works have progressed on the construction of the roads and pathways on the development.
- The tree protection remains in situ.
- The developer is using the wheel washing facilities set up by the entrance to the site. There were no problems with mud on the road when officers visited site.
- The badgers on site have been relocated following the agreed guidance and details.
- Plots 205 and 206 are having their foundations constructed.
- Plots 187-190 and 200-204 have their slabs in.
- Plots 193-199 are at ground floor level.
- Plots 2-6 are at roofline.
- Plot 1 is at the internal and external stages.
September 2024
- The developer is continuing the construction of the highway entrance from Station Road in to the site.
- The main spine road base layer around the site has commenced construction.
- The tree protection is in situ.
- The approved onsite archaeological field work is now completed.
- Plots 198-205 are having their foundations constructed.
- Plots 195-197 have their slabs in.
- Plots 193 and 194 are at ground floor level.
- Plots 1-6 are at first floor level.
August 2024
- The developer has commenced construction of the plots. Plots 1-6 are at slab level and other plots are being marked out, ready to break ground.
- The main spine road around the site has commenced construction.
- Tree protection is in situ.
- The approved onsite archaeological field work is still ongoing.
- The developer is continuing the construction of the highway entrance from Station Road in to the site.