Toggle menu

2024 updates

December 2024

  • The installation of the drainage works are continuing at the entrance to site, and around the development.
  • The construction of the spine road through the site and the spur roads is progressing. The kerbstones are being installed.
  • The tree protection remains in situ.
  • The developer is using the wheel washing facilities set up by the entrance to the site.
  • Plots 101 and 102 are having their foundations constructed.
  • Plots 189, 190 198, 199, 200 and 206 are at ground floor level.
  • Plots 187, 188 and 195-197 are at first floor level.
  • Plots 3, 4, 5, 193 and 194 are at roofline.
  • Plots 1, 2 and 6 are at the internal and external stages.
  • Land is being cleared and surveyed ready for Plots 171-175 to have their foundations constructed.

 

November 2024

  • The construction of the highway entrance from Station Road in to the site continues. The drainage is still being installed.
  • Works have progressed on the construction of the roads and pathways on the development.
  • The tree protection remains in situ.
  • The developer is using the wheel washing facilities set up by the entrance to the site. There were no problems with mud on the road when officers visited site.  
  • The badgers on site have been relocated following the agreed guidance and details.
  • Plots 205 and 206 are having their foundations constructed.
  • Plots 187-190 and 200-204 have their slabs in.
  • Plots 193-199 are at ground floor level.
  • Plots 2-6 are at roofline.
  • Plot 1 is at the internal and external stages.

 

September 2024

  • The developer is continuing the construction of the highway entrance from Station Road in to the site.
  • The main spine road base layer around the site has commenced construction.
  • The tree protection is in situ.
  • The approved onsite archaeological field work is now completed.
  • Plots 198-205 are having their foundations constructed.
  • Plots 195-197 have their slabs in.
  • Plots 193 and 194 are at ground floor level.
  • Plots 1-6 are at first floor level.

 

August 2024

  • The developer has commenced construction of the plots. Plots 1-6 are at slab level and other plots are being marked out, ready to break ground.
  • The main spine road around the site has commenced construction.
  • Tree protection is in situ.  
  • The approved onsite archaeological field work is still ongoing.
  • The developer is continuing the construction of the highway entrance from Station Road in to the site.

Share this page

Share on Facebook Share on Twitter Share by email