2024 updates
December 2024
- Development has commenced.
- All Plots 1-9 have commenced construction.
- Plots 1 and 2 have their foundations constructed.
- Plots 3-9 have their slabs constructed and are at ground floor level.
- The agreed tree protection fencing is in situ.
November 2024
Development has commenced.
- The two conservatories have been removed from the existing building;
- The roadways have commenced construction;
- Earthworks have been undertaken on site to obtain the land levels required.
- The agreed tree protection fencing is in situ.