Reference: 22/10854
Status: Grant permission subject to the completion of a S106 agreement and the imposition of conditions.

Construction of 60 dwellings; creation of two new accesses from Hill Street, parking, landscaping, open space (including ANRG) and associated works.

This application was heard by our planning committee on 8 November 2023, with a decision to give delegated authority to the Service Manager Development Management to GRANT PERMISSION subject to the completion of a planning obligation entered into by way of a Section 106 Agreement and the imposition of the conditions set out in the officer report.

 