Toggle menu

The Coal Yard Vicarge Lane Hordle

Reference: 23/110225 (a variation of planning permission 19/10007)

Status: Decided

Decision: Granted Subject to Conditions

Proposal: 

  • 10 dwellings comprising 3 pairs of semi-detached houses; 4 detached houses
  • garages to plots 7 & 8
  • associated parking
  • access & landscaping
  • demolition of existing

 

Updates

November 2024

There have been no further works carried out on site by the developer.

There are still a number of conditions to be discharged to allow construction work to take place in accordance with the granted permission.

 

September 2024

There have been no further works carried out on site since the last update.

 

August 2024

There have been no further works carried out on site.

There are still a number of pre-commencement conditions to be discharged to allow construction work to take place in accordance with the granted permission.

 

July 2024

There have been no further works carried out on site.

Construction work will be permitted to commence once any required pre-commencement conditions have been discharged.

 

June 2024

There have been no further works carried out on site.

Construction work will be permitted to commence once any required pre-commencement conditions have been discharged.

 

April 2024

There have been no further works carried out on site.

Construction work will be permitted to commence once any required pre-commencement conditions have been discharged.

 

March 2024

The variation of condition application (s73 application) reference: 23/10225 was granted permission (subject to conditions) by the planning committee on 22/02/24.

Construction work will be permitted to commence once any pre-commencement conditions have been discharged.

 

February 2024

There have been no further works carried out on site.

Variation of condition application reference: 23/10225 has not been determined yet. The developer is likely awaiting the outcome of this decision before fully commencing fully on site.

 

November 2023

There have been no further works carried out on site at the moment.

 

October 2023

Development has commenced on the site. The construction work will commence more fully in the short to medium term.

Share this page

Share on Facebook Share on Twitter Share by email