2025 updates
Regular monitoring of this site by the Site Monitoring Officer continues.
March 2025
- Construction of the plots in Phase 1 of the house build continues
- Construction of the main road and spur roads in Phase 1 , with associated drainage continues
- The road leading to the existing Augustus Park development construction continues
- The footpath leading to the existing Augustus Park development is open to the public
- Preliminary earthworks continue in the areas that will comprise the ANRG (Alternative Natural Recreational Greenspace)
- Plots 12, 59-67, 70-76, 84-93, and 108-112 are having their foundations constructed
- Plots 42-55, 77-83 and 94-103 are at ground floor level
- Plots 104-107 are at first floor level
February 2025
- The site has commenced construction of the plots in Phase 1 of the house build
- Site work is moving at pace and is well organised
- Construction of the main road and spur roads in Phase 1 is also underway, with drainage being installed
- Construction of the footpath leading to the existing Augustus Park development has begun
- Preliminary earthworks are being carried out in this section of the site in the areas that will comprise the ANRG (Alternative Natural Recreational Greenspace)
- Plots 42-55, 70-75, 83-97, 100-104 and 108-112 are having their foundations constructed
- Plots 77-82, 98, 99 and 105 are at slab level
- Plots 106 and 107 are at ground floor level