February 2025
Regular monitoring of this site by the Site Monitoring Officer continues:
- The site has commenced construction of the plots in Phase 1 of the house build
- Site work is moving at pace and is well organised
- Construction of the main road and spur roads in Phase 1 is also underway, with drainage being installed
- Construction of the footpath leading to the existing Augustus Park development has begun
- Preliminary earthworks are being carried out in this section of the site in the areas that will comprise the ANRG (Alternative Natural Recreational Greenspace)
- Plots 42-55, 70-75, 83-97, 100-104 and 108-112 are having their foundations constructed
- Plots 77-82, 98, 99 and 105 are at slab level
- Plots 106 and 107 are at ground floor level