2021 updates
December 2021
Parcel 1
- in Phase 1 Plots 75-80 are at roofline, Plot 74 has its slab laid
- in Phase 2 Plots 54-73 have their slabs laid
- in Phase 3 Plots 21 and 22 have their foundations laid and slab construction has commenced, Plots 25-27 have their foundations in and groundworks have commenced for Plot 38
- the spine road to the northern end of the site is being constructed and mains drainage is in
- foundations for the Northern spur roads are being dug and mains drainage has commenced construction in Phase 3
November 2021
Parcel 1
- the protected SANG (Suitable Alternative Natural Green space) and POS areas remain fenced off as required.
- soil and spoil is being cleared to enable various works
- the storm drainage construction has commenced through the centre of the site
- the attenuation units have been installed at the Northern end of the site and surveyors are now marking out the roadways and pathways ready for construction
- work continues on building plots 60 to 80
October 2021
Parcel 1
- the protected SANG (Suitable Alternative Natural Green space) and POS areas remain fenced off as required.
- Southern Water have installed the water service line connecting the main in the road to the site, then the footpath was reinstated, the roadway was backfilled and the temporary tarmac on the road was removed and replaced with permanent tarmac surfacing
- the foul drainage line is now installed along the Eastern edge of the development and the storm drainage will be completed shortly
- the entrance to the development and the spine and spur roads in that area are due to be tarmacked soon
- the kerbstones are currently being laid along the Eastern spur road and along the spine road into the development
- the mains drainage access points and associated gullies are also being constructed and then the base road layers will be laid
- the POS (Public Open Space) footpath top dressing has not been laid yet, this may be due to stock lead-in levels
- work continues on building plots 60 to 80